On 18 November 2026 the Supreme Court restored an arbitral award that the Calcutta High Court had reduced by half. In M/s Marino Dredgeco Ltd. v. The Board of Trustees of the Port of Kolkata (2026 INSC 1238), a bench of Justices J.B. Pardiwala and K. Vinod Chandran held that the size of an award is not, by itself, a reason for a court to interfere with it under the Arbitration and Conciliation Act, 1996.
What happened
Marino Dredgeco had dredged a riverbed and shores at Sagar Island to create a channel and basin for a shore-based pilot station for the Kolkata Port Trust. It said the work grew because of heavy siltation, and that the Port Trust had given wrong soil data and had not built protective walls. A letter of 19 July 2000 asked it to carry out additional dredging, and the pilot station was inaugurated on 17 April 2001 using the channel it had dredged.
The arbitrator awarded Marino payment for the additional work, which came to more than 70 per cent of the original contract value. The High Court cut the award to half and reduced the interest to 6 per cent on the principal. Marino appealed, and so did the Port Trust, which wanted the whole award set aside.
What the Court held
- The amount of an award cannot be altered merely because the party paying is a government entity, or because the sum looks large, when the award is backed by adequate evidence and is not perverse or patently illegal.
- A court exercising appellate power under Section 37 cannot reduce an award because it “shocks the conscience”. The High Court had not examined the measurements or invoices on which the arbitrator relied, and doing so would have meant re-deciding the merits, which the Act does not allow.
- Marino’s documents were valid evidence of the work actually done, even without a completion certificate under the general conditions of contract.
The Court allowed Marino’s appeal, set aside the High Court’s judgment and restored the award. The Port Trust’s appeal was disposed of.
Why it matters
The ruling reinforces how narrow challenges to an arbitral award are meant to be. A large claim against a public body is not a ground of challenge in itself. Someone resisting an award has to point to a legal defect in it, and courts at the Section 34 and Section 37 stages are not to retry the dispute.
Source: 2026 INSC 1238 (18 November 2026), as reported by Verdictum and LiveLaw Biz.